Videos
Project Videos
Below you will find a collection of videos displaying major project updates and milestones.
Behind The Scenes of the Broadway Curve Improvement Project
-
Jan. 31, 2023 – I-10 Salt River Bridges
+ - -
Jan. 17, 2023 – Year in Review (2022)
+ - -
Dec. 28, 2022 – MSE Walls
+ - -
Dec. 14, 2022 – The Curve App
+ - -
Nov. 30, 2022 – CD Roads
+ - -
Nov. 15, 2022 – Recycled Materials
+ - -
Oct. 25, 2022 – Shoofly
+ - -
Oct. 12, 2022 – Surveyors
+ - -
Sept. 20, 2022 – Utility Markings
+ - -
Sept. 6, 2022 – 48th Street Bridge Deck Pour
+ - -
Aug. 23, 2022 – Overexcavating
+ - -
Aug. 9, 2022 – Soffit fill
+ - -
July 19, 2022 – Guadalupe Road Bridge
+ - -
July 6, 2022 – Cranes and Beams
+ - -
June 22, 2022 – Wattles
+ - -
June 1, 2022 – Design Story
+ - -
May 17, 2022 – Surcharge Soil
+ - -
May 4, 2022 – North Pole
+ - -
April 22, 2022 – Plant Nursery
+ - -
April 5, 2022 – AC Paving
+ - -
March 22, 2022 – Community Office
+ - -
March 8, 2022 – Flagging Operations
+ - -
February 22, 2022 – Concrete Pour
+ - -
February 8, 2022: How the work zone has shifted on westbound I-10 at 32nd Street
+ - -
January 25, 2022: How rebar is used in drilled-shaft bridge foundations
+ - -
January 11, 2022: What are drilled-shaft foundations
+ -
Project Videos
-
2023
+ -January 2023: Earthwork
January 2023: US 60/Westbound I-10 Mechanically Stabilized Earth (MSE) Wall
January 2023: Salt River Bridge Drilled-Shaft Foundation
-
2022
+ -December 2022: Salt River Bridge
December 2022: Mechanically Stabilized Earth (MSE) Wall
December 2022: Eastbound I-10 at Salt River Bridge
Eastbound I-10 at Salt River Bridge
December 2022: SR 143 Mechanically Stabilized Earth (MSE) Wall
December 2022: SR 143/I-10 HOV Drill Shaft
December 2022: SR 143/I-10 HOV Bridge Drilling
SR 143/I-10 HOV Bridge Drilling
November 2022: SR 143/I-10 HOV Bridge Drill Shafts
SR 143/I-10 HOV Bridge Drill Shafts
November 2022: Northbound SR 143/I-10 Ramp Reconfiguration
Northbound SR 143/I-10 Ramp Reconfiguration
November 2022: Broadway Road Bridge Deck Pour
Broadway Road Bridge Deck Pour
November 2022: Broadway Road Bridge Deck Pour
Broadway Road Bridge Deck Pour
October 2022: 48th Street Bridge Deck Pour
October 2022: Southern Avenue Bridge Deck Pour
Southern Avenue Bridge Deck Pour
October 2022: Eastbound I-10 Miscellaneous Construction
Eastbound I-10 Miscellaneous Construction
October 2022: Eastbound I-10 on-ramp at 40th Street
Eastbound I-10 on-ramp at 40th Street
September 2022: Eastbound I-10 Rubberized Asphalt Paving
Eastbound I-10 Rubberized Asphalt Paving
September 2022: Southern Avenue
September 2022: Dynamic Message Board installation
Dynamic Message Board installation
September 2022: Sound wall removal near Southern Avenue
Sound wall removal near Southern Avenue
August 2022: 48th Street bridge deck pour
August 2022: State Route 143 work zone set up
State Route 143 work zone set up
August 2022: Western Canal multiuse bridge
August 2022: Temporary Broadway Road ramp paving
Temporary Broadway Road ramp paving
July 2022: Broadway Road girders
July 2022: Temporary concrete barrier
July 2022: Broadway Road girders
July 2022: Broadway Road girders
June 2022: Broadway Road girders
June 2022: 48th Street backfill
June 2022: 48th Street girders
June 2022: Bridge barrier
June 2022: Broadway Curve girders at 48th Street
May 2022: Workers backfill and compact the backfill material on 48th Street near Medtronic Way
Workers backfill and compact the backfill material on 48th Street near Medtronic Way
May 2022: Crews continue to relocate utilities along 48th Street and place concrete to build a column at Alameda Drive
April 2022: Work continues to relocate utilities along 48th Street
Work continues to relocate utilities along 48th Street
April 2022: Workers are building new sound walls along I-10, south of Guadalupe Road
Workers are building new sound walls along I-10, south of Guadalupe Road
April 2022: Workers dig in preparation for utility relocation along 48th Street
Workers dig in preparation for utility relocation along 48th Street
April 2022: Loader conducted earthwork near the new 48th Street bridges over I-10
Loader conducted earthwork near the new 48th Street bridges over I-10
March 2022: Workers remove the 48th Street frontage road bridge
Workers remove the 48th Street frontage road bridge
March 2022: Workers place concrete paving on eastbound I-10 south of Guadalupe Road
Workers place concrete paving on eastbound I-10 South of Guadalupe Road
March 2022: Workers move an existing light pole to a new location
Workers move an existing light pole to a new location
March 2022: Asphalt paving on eastbound I-10 south of Baseline Road
Asphalt paving on eastbound I-10 south of Baseline Road
March 2022: Construction of the new 48th Street bridges over I-10 continues
Construction of the new 48th Street bridges over I-10 continues
February 2022: Drilled-shaft foundation installation for the Alameda multiuse bridge over I-10
Drilled-shaft foundation installation for the Alameda multiuse bridge over I-10
February 2022: Construction of the new Broadway Road bridge over I-10 continues
Construction of the new Broadway Road bridge over I-10 continues
February 2022: Workers pour concrete for light pole foundations near 40th Street
Workers pour concrete for light pole foundations near 40th Street
February 2022: Workers lower a rebar cage into a drilled shaft with a crane
Workers lower a rebar cage into a drilled shaft with a crane
January 2022: Broadway Curve Concrete Pour Time Lapse
1,000 cubic yards of concrete poured for new Broadway Road bridge
-
2021
+ -December 2021: Drilled-Shaft Foundations
Drilling the drilled-shaft foundations for the new 48th Street bridges over I-10 December 2021
November 2021: Median Glare Screen Concrete Pour
Median Glare Screen Concrete Pour November 2021
October 2021: Median Glare Screen Removal Work
Median Glare Screen Removal October 2021
August 2021: Rubberized Asphalt Removal Work
August 2021: Project TV commercials
June 2021 – Geotechnical work, a necessary step before construction can begin.